By accessing this link, you will be leaving Risk Strategies website and entering a website hosted by another party. Please be advised that you will no longer be subject to, or under the protection of, the privacy and security policies of Risk Strategies website. We encourage you to read and evaluate the privacy and security policies of the site you are entering, which may be different than those of Risk Strategies.
All too frequently, design firms incur significant liability not because they did something wrong, but because they failed to carefully scrutinize their contracts and left too much room for ambiguity. Contractual certainty, and documentation of communications, becomes increasingly important when it comes to design delegation.
Together with growing pressure to shorten project schedules and decrease costs, there is a general acknowledgment that specialty subcontractors often have their own approach to fabrication and installation of project components such as curtain wall systems, fire suppression systems and the like. It is therefore becoming increasingly common for architects and engineers to delegate aspects of the project’s design to the general contractor and its subs. Almost all such delegation is done pursuant to performance specifications provided by the architect or engineer of record, but if the contract and/or project documentation is ambiguous, the design professional may look back and wish that it had provided detailed design of every connection, nut and bolt itself.
More Designers, More Exposure
Although the AIA A201-2017 provides a framework for the process of design delegation and the apportionment of fault between project participants, it provides little detail. The complexities introduced are numerous, and should be acknowledged in the contract(s) and in project documentation:
Owners’ reasonable expectations for efficiency, together with new technologies and an acknowledgment that constructors are the installation experts, suggest that design delegation will continue to expand. But the blending of roles and responsibilities gives rise to complexities that need to be dealt with on the front end. The parties’ perspectives and expectations will vary, and the only assumption that should be made is that something will go wrong. If and when it does, contract certainty and detailed project documentation will hopefully keep small problems from becoming litigable issues.
Want to learn more?
Find me on LinkedIn, here.
Connect with the Risk Strategies Architects & Engineers team at aepro@risk-strategies.com
Email me directly at DBlack@risk-strategies.com
The contents of this article are for general informational purposes only and Risk Strategies Company makes no representation or warranty of any kind, express or implied, regarding the accuracy or completeness of any information contained herein. Any recommendations contained herein are intended to provide insight based on currently available information for consideration and should be vetted against applicable legal and business needs before application to a specific client.